On October 11, 2024, Green Gold Energy was honoured to receive the 2024 Resources and Energy Export Award at the prestigious South Australian Premier’s Business and Export Awards. The South Australian Premier's Business and Export Awards celebrates the outstanding achievements of South Australian businesses over the past year.
This recognition highlights our ongoing contributions…
Green Gold Energy is a company providing turnkey solutions for Solar+ Projects, which are designed for renewable energy that combine solar power generation with BESS, Microgrid, Hydrogen, EV Charge Stations and Data Centers.
We specialise in project development, engineering, construction, operation and general contracting of the projects. Our IN-HOUSE team brings together professionals from various backgrounds.…
Dear Clients and Partners,
As we bid farewell to another eventful year, we are excited to share the key highlights and achievements of Green Gold Energy (GGE) in 2023. Our commitment to providing turnkey solutions for Solar+ Projects has led us to new heights this year, further solidifying our position in the renewable energy sector.
We consistently…
25 July 2023, Thailand Green Gold Energy (“GGE”), an Australian renewable energy turnkey solutions provider, is thrilled to announce its collaboration with Sunshine Beach Resort and Residence (“Sunshine Beach”), an award-winning beachfront development in Phuket, to sign a contract for the 1MW micro-grid project. This partnership represents a significant milestone in the nation's journey towards…
Green Gold Energy Pty Ltd. (“GGE”, Head Office: Fullarton, Adelaide; Representative Managing Director: Chongchong (John) Huang) is pleased to announce its collaboration with Daiwa Energy & Infrastructure Co. Ltd., part of Daiwa Securities Group, which provides investments in energy and infrastructure-related businesses. (“Daiwa”, Head office: Chiyoda-ku, Tokyo; President: Morimasa Matsuda) in Australia.
GGE signed…
“Green Gold Energy's first Solar & Battery Energy Storage System Project in SA”
On the 8th of August 2022, Green Gold Energy (GGE) hosted an opening ceremony for our Loveday Solar & BESS Project. The project includes two stages, the first stage is a 2MW and 5.5MWh BESS which will be completed end of this…
GGE has completed witness test along with SAPN’s commissioning officer. As of mid-day today, the site is exporting at full capacity. This project (A20, 1074 Copper Coast Highway, South Hummocks) is the 3rd 4.95MW project commissioned within the past 12 months and we are proud to see our internal capability has extended to civil work,…
Green Gold Energy and Risen Energy Australia Signed up 100MW Solar Project Development
Green Gold Energy (GGE) and Risen Energy Australia (REA) executed an agreement to jointly develop and construct 16 solar projects of approximately 4.95MW AC each in Australia within the next two years so the total project capacity will be 80MW AC and 100MW DC. Currently…
Green Gold Energy (GGE) is pleased to announce that as of 12:00pm today, the South Hummocks 4.95MVA solar farm at A20, 1074 Copper Coast Highway has been energized, after a smooth HV switching and preliminary SCADA test, witnessed by SA Power Networks connection officer and SCADA engineers. This project has proceeded into final commissioning stage…
Energy of the Future: Partnership between Green Gold Energy & Astronergy Solar Australia Group
Over the past three years, Green Gold Energy Pty Ltd (GGE) has been heavily involved in the development of solar power projects in South Australia (SA). So far, GGE has delivered 15 projects with a total scale of AC60MW and DC72MW for…
Green Gold Energy is proposing to develop a 4.95 MW solar farm located at Lot 2, PS613623 – Naring Hall Road, Numurkah, Vic, 3636.
We have enclosed some information about the project and Green Gold Energy the proposed solar farm developer.
Our plans for the solar farm are currently in the early stages of design and we are…
Green Gold Energy (GGE) is pleased to announce that our recently developed 1.98MVA solar farm at Caroona Road, Port Augusta West, has now been successfully energised. This energisation took place on the 18th of September and commenced full generation as of today, following a safe in-house HV switching and satisfactory witness test with SAPN.
It took…